PROJECT | Letšeng Diamond Mine (Kingdom of Lesotho) – Detailed Feasibility Study
Client: GEM Diamonds & Letšeng Diamond Mine
Role: Senior Project Manager
Project Value: USD160million
Key achievements:
-
Completing a Feasibility Study to transition the open pit operation into an underground operation, including all project management functions, engineering & design, mine design & layout, re-newable energy study, underground logistics, geohydrological study, capex, opex and financial valuation for project scope and schedule, ready for the next phase.
-
Completing a full tender process for a mining contractor to go into execution phase.
-
Project is not going into execution phase due to unfavorable economic evaluation.

PROJECT | Leeuwkop Shaft Project – Pre- Feasibility Study & Re-valuation
Client: Implats
Role: Senior Project Manager
Project Value: USD200million
Key achievements:
-
Completing a new Pre-Feasibility Study for the project, including all project management functions, contract negotiations, project scope and schedule ready for the execution phase.
-
Re-valuation of the 2014 Feasibility Study completed for Afplats.
-
The project did not go ahead due to the high capital estimate and the client not not have an appetite for a 10-year project.

PROJECT | Letšeng Diamond Mine – Desktop Study
Client: GEM Diamonds & Letšeng Diamond Mine
Role: Senior Project Manager
Project Value: USD130million
Key achievements:
-
Completing a Desktop Study to transition the open pit operation into an underground operation, including all project management functions, Capex, Opex and financial valuation for project scope and schedule, ready for the next phase.

PROJECT | Egoli Project – Early Works Phase
Client: Pan African Resources – Evander South Africa
Role: Senior Project Manager
Project Value: USD105million
Key achievements:
-
Completing the set-up of all project management functions, contract negotiations, project scope and schedule ready for the execution phase.

PROJECT | Mupfuti Mine Replacement Project – Bankable Feasibility Study
Client: Zimplats Ngezi – Zimbabwe
Role: Senior Project Manager
Project Value: USD128million
Key achievements:
-
Completing a Bankable Feasibility Study and Capital Budget Estimate for Bimha Decline upgrade from 2.0 Mtpa to 3.1 Mtpa

PROJECT | Moatize TSF1 Project FEL 2 – Pre-Feasibility Study
Client: Vale Mining Company – Brazil
Role: Senior Project Manager
Project Value: USD125million
Key achievements:
-
Completing a Pre-Feasibility Study and Capital Budget Estimate for a new coal processing plant.

PROJECT | Prieska Zinc-Copper Project – Bankable Feasibility Study
Client: Orion Minerals – South Africa
Role: Senior Project Manager
Project Value: USD280million
Key achievements:
-
Completing a detailed Bankable Feasibility Study and Capital Budget Estimate for new underground development.

PROJECT | Mimosa Mining Company – Pre-feasibility Study, Zimbabwe
Client: Mimosa Ming Company - Zimbabwe
Role: Senior Project Manager
Project Value: USD84million
Key achievements:
-
Completing a detailed Pre-Feasibility Study and Capital Budget Estimate for the new underground replacement mine.

PROJECT | Sintoukola – Kola Potash Project, Republic of Congo
Client: MetChem in Montreal, Canada & Technip in Paris, France.
Role: Senior Project Manager
Project Value: USD170million
Key achievements:
-
Completing a detailed Feasibility Study and Capital Budget Estimate for a new underground potash mine as part of the Technip French consortium team.

PROJECT | UMK Intermediate Crusher Project, Sishen, Northern Cape
Client: United Manganese of Kalahari (Pty) Ltd.
Role: Senior Project Manager
Project Value: USD16million
Key achievements:
-
Completing a Pre-feasibility and Feasibility Study and Capital Budget Estimate for open pit crushers and related infrastructure within time and budget.

PROJECT | Darwendale Project Feasibility Study – Darwendale, Zimbabwe
Client: Great Dyke Investments (Pvt) Ltd.
Role: Senior Project Manager
Project Value: USD476million
Key achievements:
-
Completing bankable feasibility study and capital budget estimate on time and within budget.
-
Completing project for the Owner's review and Shareholder submission for the next phase of the project.

PROJECT | Morupule Unit 5&6 Coal Supply Project PFS, Palapye, Botswana
Client: Debswana Diamond Co Pty Ltd.
Role: Senior Project Manager
Project Value: USD66million
Key achievements:
-
Completing pre-feasibility study and capital budget estimate on time and within budget
-
Completing the project for the Owner's Team Review and Board Submission for the project's next phase.

PROJECT | Leeuwkop Shaft Project, Brits, South Africa
Client: Implats Platinum
Role: Senior Project Manager
Project Value: USD600million
Key achievements:
-
Completing feasibility study and capital budget estimate on time and within budget.
-
Completing the front-end engineering and design phase as EPCM for commencement of sinking activities by sinking contractor.
-
Completing the ventilation shaft headgear and stage engineering and design within time and budget.

PROJECT | Musonoi Project, Kolwezi, DRC
Client: Metorex / Copper & Cobalt
Role: Senior Project Manager
Project Value: USD80million
Key achievements:
-
Completing engineering, design, costing and financial evaluation of concentrator plant, hydrometallurgical plant and surface infrastructure for underground mine.

PROJECT | Bokoni Platinum Mine Project, Lebowa, South Africa
Client: Anglo Platinum
Role: Project Manager
Key achievements:
-
Completing engineering, design, procurement, and construction of total surface infrastructure and underground mine layout, including handover to the client.

PROJECT | No. 16 Shaft Implementation Project, Rustenburg, South Africa
Client: Impala Platinum
Role: Project Engineer
Key achievements:
-
Completing the engineering and design for sinking contractor readiness
-
Completing the installation of all services for potable water, service water and compressed air
-
Completing all engineering and design of process flow diagrams for project implementation.

PROJECT | No. 16 Shaft Feasibility Study, Rustenburg, South Africa
Client: Impala Platinum
Role: Project Engineer
Key achievements:
-
Completing all engineering and design for costing of the services and ore handling process.

PROJECT | Palabora Underground Project, Phalaborwa, South Africa
Client: Palabora Mining Company
Role: Mechanical Engineer
Key achievements:
-
Construction and commissioning of surface refrigeration plant and water reticulation system into the underground mine
-
Construction and commissioning of service shaft and production shaft ventilation systems
-
Engineering and design of the main underground pump station.